What it calculates
Estimate a rough residential service demand for early planning.
Create a rough early-stage residential service demand estimate from connected loads and a demand factor.
Planning and estimating aid only. Verify project requirements, manufacturer instructions, adopted codes, permits, and field conditions before performing regulated work.
Use the field units shown below, then compare your result with the worked example. Changing the percentage to make a result fit a preferred service does not validate that service.
Estimate a rough residential service demand for early planning.
Connected load is reduced by the user-entered planning demand factor, then divided by service voltage and compared with common service sizes.
This is intentionally a rough planning tool and is not a substitute for a code-compliant service/load calculation.
An entered 24,000 watts at a user-selected 50% demand basis becomes 12,000 watts. Dividing by 240 volts gives 50 amps. The stored reference-size list then returns 60 amps as its next listed step.
Contractor tip: Changing the percentage to make a result fit a preferred service does not validate that service. Use the actual applicable load-calculation method and review the equipment and utility requirements.
The demand percentage is your assumption. This model does not derive permitted demand factors, account for all required loads or verify the utility service. Its reference step is not a code-compliant service calculation.
Good practice: Compare the calculated quantity with plans, specifications, product packaging and current field conditions before purchasing material.